1. Purpose & Scope
Run every approved insulation job — blown-in, batt, or spray foam — through the same disciplined production sequence. Applies to every insulation project moving from sales approval through closeout.
2. Step 1 — Sales Handoff
Sales → Production CoordinatorReceive the complete file from sales.
- Receive the job file from sales: contract, scope, measurements, photos, special notes.
- Sales tags the Production Coordinator on ProLine.
- Confirm homeowner expectations, insulation type (blown-in, batt, spray foam), R-value, areas to insulate, access notes, and any promised add-ons (air sealing, baffles, etc.).
3. Step 2 — Verification
- Confirm attic access, existing insulation, ventilation, wiring, ductwork, and any obstructions.
- Verify job photos in CompanyCam: review every photo for accuracy.
- Request missing photos when needed.
- Verify package selection: confirm choices and document them on ProLine.
- Ensure scope matches the contract and ProLine.
4. Step 3 — Move to “Ready for Install” on ProLine
- Confirm all data is complete.
- Mark the job as ready for the production workflow.
5. Step 4 — Order Materials
- Submit the material order to the supplier with correct quantities.
- Confirm delivery (or pick-up) date, drop location, and special instructions.
- Upload order confirmation to the job file in ProLine.
- Track every receipt for materials in ProLine and/or CompanyCam.
6. Step 5 — Schedule Crew
- Assign the insulation crew based on job type and complexity.
- Confirm crew start time and equipment needs: PPE, blower, hoses, ladders, scaffold.
7. Step 6 — Confirm With Sales (Sales Confirms With Homeowner)
- Notify the salesperson of the scheduled date.
- The salesperson confirms with the homeowner.
- Wait for homeowner confirmation before finalizing.
8. Step 7 — Move to “Job Scheduled” on ProLine
- Update CRM status and the internal schedule.
9. Step 8 — Pre-Install Preparation (Day Before or Morning Of)
Yard Sign
- Place a yard sign in a visible, pre-approved location.
Before Pictures
- Take attic-access photos, insulation levels, ductwork, and any pre-existing issues.
Cover Anything That Needs Protection
- Protect flooring, walls, and homeowner belongings near attic access.
Check Ventilation
- Verify ventilation and note any changes that will need to be made.
10. Step 9 — Move to “In-Progress” on ProLine
- Update the CRM when the crew begins work.
11. Step 10 — Verify Material Delivery
- Confirm the correct insulation type and quantity arrived on site.
12. Step 11 — Oversee Job Install
- Ensure proper air sealing.
- Install baffles and ventilation as needed.
- Install insulation to correct depth and R-value.
- Verify foam application (when applicable).
- Monitor safety and cleanliness.
13. Step 12 — Get Extra Materials (If Needed)
- Acquire additional insulation or supplies quickly.
14. Step 13 — Job Cleanup
- Vacuum the attic-access area.
- Remove debris and containment materials.
- Confirm the attic access is sealed properly.
15. Step 14 — Finalize With Homeowner
- Show before/after photos.
- Explain the new insulation depth and improvements.
- Answer questions.
16. Step 15 — Take Returns to Vendor
- Return all unused items to the vendor they came from.
17. Step 16 — Move to “Job Complete” on ProLine
- Update the CRM.
- Upload all final documentation to ProLine and CompanyCam.
18. Step 17 — Hand Back to Sales Team
- Notify the salesperson the job is complete.
- Sales handles final inspection, invoicing, and closing.
20. Revision History
| Version | Date | Summary | Approved By |
|---|---|---|---|
| 1.0 | 2026-04-29 | Format reset; cleaned up duplicated text; ProLine/CRM/PPE/R-value spelled out; active voice; standard related/revision blocks. | Production Manager |